St George Mining ASX SGQ: Araxá Project Resource Grows to 111.2Mt
St
George Mining Reports Major Progress at Araxá
St George
Mining Limited (ASX: SGQ) has reported significant progress at its Araxá
Niobium and Rare Earths Project in Brazil during the September 2026 quarter.
The
company's latest quarterly report highlights an expanded mineral resource,
encouraging drilling results, environmental permitting progress and continued
pilot plant development.
The Araxá
Project remains central to the company's growth strategy as it advances its
plans to develop a major niobium and rare earths operation in Brazil.
For
investors following St
George Mining ASX SGQ, the September quarter results provide an update
on the company's exploration, development and funding position.
Araxá Mineral Resource Increases to 111.2 Million
Tonnes
One of
the major developments during the quarter was the increase in the Araxá Mineral
Resource Estimate to 111.2 million tonnes (Mt).
The
updated resource contains:
- 3.57% Total Rare Earth
Oxides (TREO).
- 0.70% Magnet Rare Earth
Oxides (MREO).
- 0.68% Neodymium and
Praseodymium (NdPr).
- 0.57% Niobium pentoxide
(Nb₂O₅).
The
estimate includes approximately 98 million tonnes of TREO, 760,000 tonnes of
NdPr oxides and 630,000 tonnes of niobium pentoxide.
Measured
and Indicated Resources increased by 155% to 75.2Mt, representing approximately
68% of the total resource.
The
updated resource strengthens the development potential of the St
George Mining Araxá Project and provides an important foundation for
ongoing feasibility work.
Drilling Results Highlight High-Grade
Mineralisation
St George
Mining continued its drilling programme during the September quarter, reporting
several significant intercepts at Araxá.
Some of
the notable results included:
- AXDD166: 135.1m at 4.86% TREO,
including 69.0m at 7.33% TREO and 20.0m at 12.65% TREO.
- AXDD142: 207.0m at 2.60%
TREO.
- AXDD165: 150.5m at 3.66%
TREO, including 67.0m at 5.46% TREO.
- AXDD167: 150.2m at 3.49%
TREO and 0.72% Nb₂O₅.
These
results demonstrate broad rare earth and niobium mineralisation across the
project area.
The
company also reported that mineralisation remains open in several directions,
including at depth, providing further opportunities for resource expansion.
Drilling
at East Araxá is also progressing to support a maiden mineral resource estimate
for the area.
Environmental Permitting Moves Forward
Another
important milestone was the submission of the Environmental Impact Assessment
(EIA) and Environmental Impact Report (RIMA) to the State Environmental
Foundation of Minas Gerais (FEAM).
The
documents cover the proposed open-pit mine and industrial complex, including
processing facilities, refining infrastructure, waste management and supporting
operations.
The
submission follows approximately 14 months of environmental studies and
fieldwork.
The
permitting process will involve three key licences:
- Preliminary Licence.
- Installation Licence.
- Operation Licence.
These
approvals are required before the proposed mining and industrial operations can
proceed through the relevant development stages.
The
company is advancing its permitting activities alongside the feasibility study
being led by Worley.
Pilot Plant Development Progresses
St George
Mining also advanced metallurgical testwork during the quarter.
A pilot
plant study commenced at CIT-SENAI in Belo Horizonte, Brazil, using
approximately nine tonnes of near-surface saprolite material collected from the
Central Araxá area.
The
programme involves grinding, magnetic separation and flotation to produce
separate niobium and rare earth concentrates.
Results
are expected in the fourth quarter of 2026.
The
company is also constructing a larger pilot plant at the Araxá site in
collaboration with CEFET, the Federal Center for Technological Education of
Minas Gerais.
The
planned facility will have processing capacity of up to 300kg per hour and is
expected to produce niobium concentrate, rare earth concentrate, mixed rare earth
carbonate and rare earth oxides.
Completion
of the St George Technological Centre is expected in December 2026, with pilot
plant operations scheduled to begin in January 2027.
Rare Earths Processing Centre Supports Brazilian
Supply Chain
During
the quarter, St George Mining entered into a collaboration with the State of
Minas Gerais and the Lima & Pergher Group to advance plans for a potential
rare earths processing centre.
The
proposed facility is intended to support rare earth projects across the state,
including the Araxá Project.
The
initiative aims to develop a domestic mine-to-magnet supply chain by processing
Brazilian rare earth feedstock within the country.
The
proposed centre would refine rare earth concentrates and produce materials used
in permanent magnets.
This
development could strengthen Brazil's position in the global rare earths supply
chain and create additional opportunities for the company.
St George Mining Strengthens Its Financial Position
St
George Mining reported a cash balance of A$86.195 million as at 30
September 2026.
The
company completed a A$60 million placement during the quarter, with
participation from Hancock Prospecting, which committed A$20 million to the
raising.
The
placement was completed in two tranches, raising approximately A$42.4 million
and A$17.6 million before costs.
The
company also received approximately A$929,000 from the exercise of listed and
unlisted options.
According
to its quarterly report, St George Mining had no loan facilities in place at
the end of September 2026.
The
available funding provides support for ongoing exploration, metallurgical
testwork, permitting and feasibility activities.
Key Milestones to Watch
Several
upcoming developments could shape the company's progress over the next few quarters:
- CIT-SENAI pilot plant test
results expected in Q4 2026.
- Completion of the St George
Technological Centre expected in December 2026.
- Pilot plant operations
scheduled for January 2027.
- Continued drilling at East
Araxá.
- Progress through
environmental licensing stages.
- Further feasibility study
work led by Worley.
- Development of the proposed
Minas Gerais Rare Earths Processing Centre.
These
milestones will help determine how the company progresses from resource
development towards potential future production.
Conclusion
St George
Mining closed the September 2026 quarter with an expanded 111.2Mt Araxá mineral
resource, encouraging drilling results and progress across environmental
permitting and metallurgical testwork.
Its A$86.195
million cash position also provides financial support for the next stages of
project development.
For
investors tracking St
George Mining ASX SGQ, the upcoming pilot plant results, feasibility
work, East Araxá drilling and permitting milestones will be important
developments to monitor.
Disclaimer:
This article is for informational purposes only and does not constitute
financial or investment advice. Readers should conduct independent research
before making investment decisions.